Right of Way, Easement, and Encroachment Closures



Right-of-Way and Easement Closures

Engineering Services provides an application for review of requests to close right-of-way or easements due to development constraints or title issues. This process is often utilized for those experiencing these typical scenarios:

Applications must be completed and returned to:

City of Tulsa Public Works Engineering Services
Attn: Utility Coordination
175 E 2nd Street, Suite 13-401, Floor 13.
Tulsa, OK 74103

Applications may also be submitted by email to: [email protected]

For questions or concerns please contact Gary McClendon, Utility Coordination Supervisor at (918) 596-2578, or Tony Glynn, Utility Coordination Manager at (918) 596-9245.

Encroachment Agreements

Engineering Services provides an application for review of requests to occupy right-of-way or easements with private improvements. Typical scenarios for requests of this nature are as follow:

Applications must be completed and returned to:

City of Tulsa Engineering Services
175 E 2nd Street, Suite 13-401, Floor 13.
Tulsa, OK 74103

Applications may also be submitted by email to: [email protected] 

For questions or concerns please contact Gary McClendon, Utility Coordination Supervisor at (918) 596-2578, or Tony Glynn, Utility Coordination Manager at (918) 596-9245.