Street Rehabilitation Project to Begin Monday, Oct. 17, on East Eighth Street, Cincinnati Avenue to Kenosha Avenue

10/14/2022
This article was archived on 9/30/2023

A street rehabilitation project is scheduled to begin during the 10 days following Oct. 17 on East Eighth Street between Cincinnati Avenue and Kenosha Avenue, and then on East Seventh Street between Detroit Avenue and Kenosha Avenue. This project will not affect access to highway ramps.  

During this project, traffic may be reduced to two lanes in the work area. Access will be maintained for all residents and businesses. The project is anticipated to start on Eighth Street, and then move to Seventh Street.  

This project also includes driveway approaches, sidewalk maintenance, stormwater drainage improvements and waterline replacement. Completion of the project is estimated for September 2023. 

The City of Tulsa has contracted with Crossland Heavy Contractors for this $4,146,000 Improve Our Tulsa project.